Developing
Issues
Construction Waste: (i) Contractors are to maintain
a waste management log detailing disposal of waste
materials. To date, Allteck has not provided a Waste
Storage, Handing and Management Plan, as one of the
required EPPs.
ii)
Measures to be taken during drilling in the Potential
Acid Rock area and disposal of drilling dust.
Allteck has not supplied copies of its emergency response
and Spill Prevention Plan, including details of their
spill containment protocols.
Environmental
Management and Mitigation Measures Implemented
Terrestrial
Wildlife and Vegetation Management Commitments
BCTC has committed to minimizing the clearing of natural
habitats and removal of structures during the passerine
bird nesting and breeding period, which is typically
from March 15 to August 15 in the lower mainland and
Gulf Islands. Where work is required during this period,
a nesting bird survey program is being conducted by
Golder’s wildlife biologists prior to clearing
and brushing activities to identify and protect active
migratory bird nests, in accordance with protocol
established by Canadian Wildlife Service (CWS).
Archaeological
Concerns
White Pine identified that two Culturally Modified
Trees (CMTs) exist on Salt Spring Island near structure
number 52/1. These areas have been flagged off with
a 10m buffer to avoid potential disturbance.
Recommendations
a)
Issues Requiring Immidiate Action
i)
Allteck (White Pine as Alteck's Environmental Monitor)
is to submit the following activity, Environmental
Protection Plans (EPPs):
•
Sediment and Erosion Control Plan
• Hazardous Materials Handling Plan
• Emergency Responsed and Spill Prevention Plan
• Concrete Handling, Placement, and Curing Plan
• Occupational Health and Safety Plan
• Traffic Management Plan
• Hazardous Materials Control Plan
• Concrete Handling, Placement and Curing Plan
Contractor Environmental Pre-Work Orientation Record
needs to be completed and signed-off for each of Allteck,
Dent and Pacific Blasting.
White Pine is to submit the Contractor Environmental
Per-Work Orientation Record with detailed schedule.
ii)
Allteck is to minimize disruption of herptile breeding
periods and avoid mortality of amphibians and reptiles.
The pond at transmission structure number 54/1 on
Salt Spring Island provides potential habitat for
the red legged frog, which is a species of concern
under federal (Species at Risk Act – SARA) legislation.
Should draining of this pond be required, it will
be necessary to undertake an amphibian salvage subject
to terms and conditions of a Wildlife Permit.
b)
Developing Issues
Allteck and their subcontractors (specifically Dent)
are to maintain a waste management log detailing disposal
of waste materials, as referenced in the EMP. White
Pine as Environmental Monitor is to inspect this log
for compliance.
The silt fence that failed between structures 53/1
and 53/2 should be reinstated and inspected by White
Pine prior to further work in this area of Salt Spring
Island.
Anchor holes drilled within bedrock have resulted
in small piles of drilling dust at each site. White
Pine’s Daily Environmental Reports propose the
drilling dust be used as backfill when completing
the footing works.
In view of the acid rock drainage potential of the
rock on Maple Mountain, and since the rock drilling
dust is a contrcution waste with no structural quality
as backfill, Go0lder recommends that the rock drilling
dust be collected and removed offsite to an approved
landfill.
Allteck is to restore disturbed riparian areas along
ROW to preconstruction conditions. White Pine is to
document these activities in the Daily Environmental
Monitoring Reports.
Golder personnel (qualified professionals) are currently
undertaking on-going bird nesting surveys in accordance
with this commitment.
Allteck is to control the introduction and spread
of noxious weeds and invasive species.
Allteck is to follow mitigation measures per Wildlife
Risk Management System, Fuel Management Handbook and
Vegetation Management Standard VM 06.190, and to follow
applicable provincial wildfire legislation. White
Pine as Allteck’s Environmental Monitor is to
monitor this commitment. |