Introduction
The rapid strides of economic development, particularly
in urban areas, need intensive use of natural resources,
that affects the environment leading to ecological
problems.
The compilation of environmental baseline data is
essential to assess the impact on environment due
to the project activities. The environment includes
water, land, air, ecology, noise, socio-economic issues
etc.
General
Environment
The average elevation of Delhi plains is around 198-200m
above MSL. River Yamuna flows across the eastern flank
of the city. Many small water courses intersect the
terrain, causing a variation in relief. However, average
gradient of terrain is gentle, of the order of 1 to
3m/km. The area has mature topography with isolated
hillocks.
Water
and Soil
The water and soil samples had been tested for chemical
analysis. Total dissolved solids, and flouride in
the water sample are on higher side and need treatment
if used for drinking. Most of the other parameters
are within the permissible limits.
Composition of soil shows predominance of sand over
silt and clay. PH of the soil sample indicates that
soil is alkaline in nature. Based on this data, it
could be concluded that sub-soil and underground water
are unlikely to undergo any deteriorating effect due
to proposed Metro structures and foundation
Flora
of the Project Area
Tree
survey was carried out along the proposed alignment.
Trees are to be cut on the land where the stations
are proposed and on the land that will be permanently
acquired at station locations. The main species along
the alignment are Pipal, Neem, Kikar, Eucalyptus,
Ashok, Ficus and Bakaan, etc. No rare or endangered
species of trees had been noticed during field studies.
About 14 trees exist on the proposed alignment.
Air
Quality
As
a part of this study, ambient air quality monitoring
(AAQM) had been carried out by setting up ambient
air quality monitoring station at Dwarka area for
the parameters SPM, CO, SO2, and NOx. The ambient
air quality data indicates much higher value of suspended
particulate matter than the prescribed limits established
by CPCB at the monitoring station. However, the values
of SO2, NOx and CO are within the permissible limits.
Seismicity
& Noise Levels
Noise
levels were measured at Dwarka area at 2.0 m away
from source as per standard practice. It could be
concluded that the noise levels recorded are higher
than the prescribed permissible levels of 65dBA (day)
and 55dBA (night). Since the project area falls in
Zone IV of Seismic Zoning Map of India, this necessitates
the need to be considered for design purpose for civil
engineering structures and while finishing civil designs.
Positive
Environmental ImpactsPositive
environmental impacts identified and discussed are
(a) traffic congestion reduction, (b) quick service
and safety, (c) less fuel consumption, (d) reduction
in air pollution, (e) better roads, and (f) employment
opportunities.
Negative
Environmental Impact)
1) Impacts Due to Project Location
i)
Change of land use:
The alignment changes from underground to elevated
section. For different components of this corridor
3375 sqm of DDA land shall be acquired. The cost of
land is already incorporated in the project.
ii) Loss of trees:
Due to the proposed Metro construction, approximately
14 trees are likely to be lost. The total value of
these trees is Rs 9800. As per the Department of Forests
stipulations, about 140 plants are required to be
planted; their total cost works out to be Rs 31000.
2)
Impacts Due to Project Construction
i)
Soil Erosion and Health Risk at Construction Site:
a)
Run off from unprotected excavated areas, and underground
tunnel faces can result in excessive soil erosion,
especially when the erodability of soil is high. Mitigation
measures include careful planning, timing of cut and
fill operations and revegetation. In general, construction
works are stopped during monsoon season.
b)
Problems could arise from dumping of construction
spoils. It is proposed to have readymade mix at site
directly from batching plant for use at site; materials
like steel etc will be housed in a fenced area.
c)
Health risks include disease hazards due to lack of
sanitation facilities. Mitigation measures include
proper water supply, sanitation, drainage, healthcare
and human waste disposal facilities.
d)
Traffic diversions and risk to existing buildings
during construction: Minimum traffic diversions on
roads will be required as the stretch is very small,
as the grade and elevated section is mostly on barren
land. In underground portion, the building line is
considerably away from the proposed cut and cover
and tunnels. Hence, no risk is foreseen to adjacent
buildings.
e)
Impact on water quality: Construction activities may
have an adverse impact on water bodies due to disposal
of waste. The waste could be due to the spillage of
construction materials. Contamination of ground water
can take place, if the dump containing above substances
gets leached and percolates into the groundwater table.
This is not the case with the present project, as
the activity does not involve usage of any harmful
ingredients.
f) Disposal of soil during construction of underground
Metro projects is a specialized and complex task.
Owing to paucity of space in the busy cities and for
safety reasons, surplus earth would have to be transported
to the nearby site of DMRC requiring earth filling.
During construction, about 8476 m3 of soil is likely
to be excavated. Out of this, 848m3 (10%) is likely
to be reutilized in filling. The balance 7628m3 (90%)
will be disposed of.
3)
Impacts Due to Project Operation
i)
Oil Pollution: Oil spillage during change of lubricants,
cleaning and repair processes, in the maintenance
of rolling stock, is very common. The spilled oil
should be trapped in grit chamber for settling of
suspended matter. The collected oil should either
be auctioned or incinerated, so as to avoid any underground
water contamination.
ii)
Noise: The main sources of noise from the operation
of trains include: engine noise, cooling fan noise,
wheel rail interaction, electric generator and miscellaneous
noises like passenger’s chatting. The operation
of metro will however reduce the noise level by about
7-9%.
iii)
Accidental Hazards: In view of the hazards potential
involved due to failure of system and accident, the
onsite and off site emergency measures have been formulated
and will be implemented.
iv)
Metro Station’s Water Supply and Refuse: Public
Health facilities, such as water supply, sanitation
and toilets are very much needed at the stations.
An amount of 45 litres per day water supply to persons
working at stations has been recommended by CPHEEO.
As also water for fire emergency is required. This
works out to about 1,30,000 litres/day. Also the refuse
will be very little to the tune of 3g/day/person.
Both these have already been considered in CP - Dwarka
section and New Delhi-IGI airport section. respectively.
v)
Visual Impact: The construction of the above corridor
will bring about a change in visual look of the streets
through which it will operate. An architecturally
well designed structure, could be aesthetically pleasing
and able to reduce impact due to visual disfiguration.
vi)
Vibration Control: Vibration emanates from rail wheel
B interaction and the same can be reduced by minimizing
surface irregularities of wheels and rail, improving
track geometry, providing elastic fastenings, and
separation of rail seat assembly from the concrete
plinth with insertion of resilient and shock absorbing
pad.
Environmental
Management System
The Environmental Management System constitutes provision
of an Environmental Division, which should be staffed
by an Environmental Engineer/Officer, an Environmental
Assistant and two other assistants (miscellaneous
works). The task assigned should include supervision
and coordination of studies, monitoring and implementation
of environmental mitigation measures. An Environmental
Adviser shall review progress of the division every
year. Cost of such an establishment is attributable
to another system of the entire metro. The Environment
Management Plan should be implemented in phases, so
that optimum benefit could be achieved and it should
be synchronized with the construction schedules. |